Fairview Interlachen Sanitary Sewer Rehabilitation Project

The City of Fairview will rehabilitate the Interlachen sanitary sewer mains, with construction anticipated in early December 2019 through early February 2020.

The Interlachen sewer mains are concrete pipes that convey sanitary sewage to the Interlachen Pump Station along a narrow, two-mile corridor between Blue Lake and Fairview Lake. They have direct connections from private homes along NE Interlachen Lane and receive flows from upstream gravity collector lines and the Blue Lake Pump Station.

These pipes are nearly 50 years old and showing signs of deterioration. Repairs are needed to protect public health and the environment.

The sewer mains are routed in Interlachen Lane, Lachenview Lane, 216th Avenue and the back yards of homes on the north shore of Fairview Lake. The City has given careful thought to completing the work with the least impact on area neighbors and the traveling public.

Cured-in-Place Pipe (CIPP) Technology

The City gave careful thought to the most effective and least intrusive way to approach the project and selected Cured-in-Place Pipe (CIPP) technology for the least possible impact to area neighbors.

CIPP technology has been used in North America for almost 40 years to structurally renew and extend the life of buried pipelines without costly and intrusive excavation.

During CIPP installation, crews insert a resin-impregnated tube into the existing pipe, expand the tube, and cure or harden the tube under pressure, forming a restored and fully structural pipe.

Project Area and Upcoming Work

The map below shows the anticipated construction in your neighborhood over the next two weeks. This is intended as a general guideline only as the contractor’s schedule is subject to change. Please note the following regarding temporary sewer interruption associated with this work:

  • A notification will be placed on your front door 24-48 hours prior to the interruption of sewer for your home. 
  • Please refer to the FAQ page.
  • If you have additional questions please contact Kelly Uhacz, City of Fairview Public Works, 503-674-6222.

NE Interlachen Lane will be closed at various locations between NE Fairview Lake Way and NE 216th Avenue for sanitary sewer work beginning Monday, April 6 through Wednesday, April 15th between the hours of 7:00 AM and 7:00 PM.

fairview/interlachen-sewer/ne-interlachen-road-closure-06-15apr20
fairview/interlachen-sewer/ne-interlachen-road-closure-06-15apr20

Schedule

Construction is anticipated to begin in early December through early February 2020 and take approximately three months to complete. 

Project Schedule Graphic
Project Schedule Graphic

Frequently Asked Questions

Construction Overview

CIPP Installation
CIPP Installation

This December and January, the sanitary sewer throughout the Interlachen neighborhood will receive maintenance and restoration to keep it operating safely and efficiently.

Work will start the first week of December and continue for six to eight weeks. Crews and equipment will be in the area, including roadways and sewer easements across private property, Mondays through Fridays and possibly some Saturdays, from as early as 7:30 a.m. to 6 p.m.

The sewer will still function during most of the work, thanks to bypass pumping. The area won’t be disrupted with open trenches, thanks to cured-in-place pipe technology.

You’ll need to restrict your use of the sewer for one day during construction. Read on for details. Noise, dust and odor are possible during the work.


What (and when) is restricted sewer use?

A typical sewer lateral
A typical sewer lateral

Your home’s sewer pipe, called a “lateral,” connects to a main sewer line. For one day during construction, your lateral will be plugged while crews work on the main line. You’ll need to restrict sewer use during construction hours to avoid backup into your home. Restricting your sewer use means don’t:

  • Take a shower.
  • Drain a bathtub.
  • Run a washing machine or dishwasher.
  • Flush toilets

If you anticipate particular difficulties in curtailing toilet use, please contact Kelly Uhacz, City of Fairview Public Works, at 503-674-6222 to discuss your particular situation.   

The date your lateral sewer line will be plugged depends on your location as work progresses. The contractor, Iron Horse, will leave a notice with contact information on your front door at least two days before your restricted-use day. Someone with Iron Horse will also knock on your door when you are free to resume full sewer use.


What about driveways, school buses and garbage trucks?

In general, the work won’t block driveways. If the contractor does need to use someone's driveway, it will coordinate with that homeowner in advance.

The contractor will also coordinate construction to minimize disruption to school bus routes and garbage pickup.


What is "cured-in-place pipe" (CIPP) technology?

Bypass Pumps with Diesel Generator in background
Bypass Pumps with Diesel Generator in background

Cured-in-Place Pipe (CIPP) technology involves inserting a resin-impregnated tube into an existing pipe, expanding the tube against the pipe, and curing or hardening the resin using ultraviolet (UV) light, hot water, or steam under pressure. The result is a jointless, fully structural pipe tightly fit against the existing pipe.

CIPP technology has been used in North America for almost 40 years to structurally renew and extend the life of buried pipelines without costly and intrusive excavation.

UV-cured CIPP is inserted by "pull-in," which means pulling a resin-impregnated tube through the existing pipe:

  • Before installation, a plastic pre-liner sheet is pulled into place and lubricated so the resin-impregnated tube can glide easily through the existing pipe.
  • The tube is then inflated and pressurized against the host pipe, allowing the UV light train, equipped with an inspection camera, to inspect the tube for defects.
  • After the inflated tube is inspected, the UV light bulbs are turned on and the pipe is cured.

UV-cured CIPP installation typically requires five major pieces of equipment:

  • A closed-circuit television (CCTV) truck for inspecting the pipe before and after installation.
  • A truck and trailer for transporting the uncured tube.
  • A combination vacuum and hydro-jetting truck to clean the line of debris and other obstructions.
  • A winch to pull the pre-liner and tube through the existing pipe.
  • A truck to monitor and control UV curing.

Each piece of equipment is needed at separate times. For example, once the pre-installation television inspection is completed, the CCTV truck is moved away and the next truck brings the liner over the manhole.


How does bypass pumping work?

Bypass pumping continues sanitary sewer service during construction. It occurs continuously during CIPP installation and post-installation video inspection.

Bypass pumping for this project will be specified for reliability:

  • A standby backup pump will be required at all times.
  • The bypass discharge pipe will generally be high-density polyethylene (HDPE) with quick-connect couplings, or lay-flat hoses for low-flow mainlines.
  • The bypass discharge pipe will be routed in the roadway between manholes and along the lake shoreline as required for each section of sewer lining.

What’s a sewer “lateral”?

It’s a private sewer pipe from your home to the public sewer main. Its name comes from generally running in a sideways direction compared to the sewer main.

As shown in the diagram, laterals have both upper and lower parts. The upper lateral runs from the home or business to a cleanout at the sidewalk or sometimes the property line. The lower lateral runs from the cleanout to the sewer main. If no cleanout is in place, the lateral is usually not considered to have separate upper and lower parts.

Laterals are the responsibility of the property owner. The Interlachen Sewer project will address mainline sewer rehabilitation only.


What’s a sewer "easement"?

It’s an area where a city or other agency has the right to enter, maintain, repair, inspect, improve, renovate and replace things such as sewer pipes and manholes; and to keep clear access to that area.

Easements on this project are in off-street areas.

Easements limit some rights of landowners. For example, the sewer easements along the Fairview Lake north shore, grants the City of Fairview the right to enter properties to access sewer pipes along the shoreline.


How will disturbed areas be restored?

CIPP installation is trenchless, minimizing the need for excavation. If the ground is wet or soft during the work, crews will take measures to mitigate disturbance outside the roadway.

Pre-construction photos will document the conditions of surrounding properties. Crews will restore the area to the best possible conditions once construction is complete. Since the CIPP technology and bypass pumping work are staged above ground, restoration is anticipated to be relatively minor.

Contact Us

Submit a Comment


If you would like a response, or if you want to sign up for the mailing list, please tell us how to get in touch: (Check all that apply)


Submit Comment